Comprehensive Patriot Place Review
Committee Meeting
Minutes of October 23, 2006
Chairman Mark Sullivan
opened the meeting at 7:00 p.m.
Members present: Anthony LaChapelle, Paul Feeney, John
Michelmore, Arthur Barrett, Neil Forster, and Arthur Muldoon (alternate) – Bert Delaney and Bill Buckley were
excused
Minutes from the October 16th
meeting were approved motion by Mark
Sullivan second by Neil Forster
approved by all.
A statement from Bill Buckley was read into the record
by Neil Forster (attached) It was read prior to Leo Potter's statement since it
addressed some of the Water and Sewer issues.
Chairman Sullivan
informed the group that ConCom was working with the Bass Pro Shop only.
Leo Potter was
introduced and gave a statement of the Water & Sewer Department’s
involvement with the project to date.
W&S
have begun to meet with town consultants and the Patriots, they have reviewed
relevant plans and given their suggestions and comments.
A
main concern is the need for improvement of the water main on Route One. Once the road is widened plans should be
made for the laying of new pipe, upgrading from the existing 10” pipe to a 12” pipe. The existing 10” piping is prone to leaks and problems, there is
about 3000 to 4000 feet in the problem area.
It was noted that the Commonwealth presently allows the Town to pump
water at a rate of 2 Million gallons a day; the Patriot’s will require about 80
Thousand gallons a day more, the State Hospital Development also. W & S has
already submitted a request to the State for permission to pump an additional
amount
W&S
are in discussions about the future of the leaching bed for the town and
Patriots treatment plants. These
discussions will continue, they have only had preliminary discussions at this
point. The Patriots intend on fully utilizing their treatment plant only. Nothing will be ready or available for other
additions by the Town. The leaching field in question is an approximate 125,000
gallon per day capacity bed that was originally reserved to accommodate further
expansion along Route 1. It is in an
area known to have the required absorption capability, there are other areas in
the vicinity that are not capable. The only other capable areas left to the
Town are the State Hospital area where Recreation facilities are presently
contemplated and the Spring Street area.
So there
is still space available for the town to use as a leaching field, however the
town must reach a decision before the
space is filled or paved over. W&S have raised the question about putting
piping in the leaching area for the Town prior to paving but the Patriots have
not responded.
Mr.
Potter stated that the leaching field is the towns forever, there is no sunset
clause, however, there is a sunset clause on the treatment plant, the date is
the year 2010. The town could assume
responsibility for the Patriots plant and a town’s plants after that date.
The
town has an option to build a one-million gallon treatment facility on the site
with a 125 gallon bed with reserve if needed
The
fire-flow test is at 2000 gallon per minute, which is more than adequate.
In summary the W&S top
priorities and concerns for this project are that the Water Main on Route One
be replaced, there have been four main breaks in the past couple years and the
time time to work on the breaks is always very limited because of the heavy
volume of traffic, etc. Need to upgrade
to 12” piping. Leo noted that this can
and will be very expensive.
W&S
ultimately would like the town and the Patriots systems to integrate
together. The best plan should be put
in place that will benefit the town as well as handle the additional usage by
the Patriots area.
The W&S also want to ensure
that the new system is of sound construction and is properly completed. Also, it must be kept in mind that the town
must inform Mansfield of their plans so that Mansfield can proceed with their
improvement plans.
Leo noted that this should not
have any affect on man hours for his department, stating that permit fees
should compensate for any additional time spent by his staff or consultants for
the department.
Mark Sullivan
questioned the board on the Advertising rights for the Water Tower. It was stated that this may play a role in
negotiations with the Patriots. It was
noted that the water tank is under the jurisdiction of the W&S Department,
all proposals must be brought to them and then after their recommendation is
signed off on, it is brought to the Selectmen for sign off. No one could come to a definite answer about
who has the final say. Mark to
investigate more.
John Michelmore asked
Leo, et al, if there was some way of having a blown up view of what is actually
being proposed for use at our future meetings. Chairman Mark Sullivan suggested
that a copy be obtained from consultant MAGUIRE or Town Planner Marc Resnick
for the use of the Committee.
Michael Kelleher of the Foxborough Fire gave a slide
presentation showing what the impact of Patriots Place will have on the
department.
The report’s concerns are that the Fire Department is
already short staffed compared to area stations and that, in the best interest
of the town, the personnel for the department should be increased by 14. These concerns address all the added
developments that are being constructed in Foxboro in addition to the adding of
Patriots Place. Five additional workers should be in place during construction
of Patriots place, so that they’re trained and ready when the complex is
complete.
At this point the current
replacement of equipment will continue as usual, the department is not looking
for additional equipment. The main
focus and concerns are with the need for additional personnel.
John Michelmore
inquired about the Patriots going out for their EMT Services. Chief
MacNamara reminded everyone that the FFD is the licensed 911 responder,
regardless. If the outside ambulance
has taken someone from Patriots area, they must call for FFD to help.
Captain Don Treannie
reminded the Committee that there are many other activities that happen at the
Stadium and that FFD is constantly making the run up there. During the construction of the new stadium
there were many calls for services.
Neil Forster read his
suggestion for the committees Mission Statement…
It is the intent of this
Committee, acting in the interests of the Town of Foxborough and it’s
residents, to study and analyze the overall impact of the proposed Patriot
Place Mall and supply the Board of Selectmen with a summary containing a
comprehensive set of suggested guidelines and actions to be taken, both in
advance of construction; during construction; and during occupation of the Mall
by potential Lessees.
In pursuit of this Mission a
Fiscal Impact Study will be undertaken which will also include a broad Economic
Impact Study. While respectful of the
jurisdictions of various Town Departments it is considered crucial to look to
all Boards for information and guidance and to suggest to them any actions
deemed to be vital for taking at this early point in time.
It was asked that each board
member review the statement and come back with their comments/suggestions.
Neil Forster made a
motion to ask permission from the Board of Selectmen for their approval to
publish a website for the committee as a portal to keep the public informed on
the workings of this committee. The
motion was seconded by Paul Feeney,
all in attendance were in favor.
Citizen Input
Jim DeVellis
questioned what is the common glue between the planning board, and this
committee. He expressed his concerns
that although this committee is working diligently, that the Planning Board has
the final sign off and all this could happen while this committee is still
working on its’ findings. What is the
time frame this committee has to work with?
It was stated that once the public meetings are concluded there is a 30
day time limit to submit the findings.
Neil and Tony are working together to firm this
situation up.
Nancy Campany informed
that e-mail is not a form of discussion to be used with an open meeting. Mark will investigate the laws on open
meeting to see if e-mail is allowable.
Nancy also is concerned that our
hired consultant should be well versed in the large commercial
development. Chairman Mark stated that
the committee has the same concerns and that the request to hire a consultant
is in the works and has been approved.
John Michelmore
motioned to adjourn, seconded by Paul
Feeney all were in agreement at 9:30 p.m.
Submitted,
Lynda Walsh
HOME MEMBERS SCHEDULE ARCHIVE PLANNING BOARD XXXXX